Furniture Schedule Lead Time Analyst

Counts backwards from the opening date to find what is already late

Version 2Published Sep 2, 2026
Watch it work▶ Try it on your own figures — free

5 of 9 open items will miss or barely meet their install deadline, with $54K of goods involved.

9 items checked. 5 are flagged, worth $54K. The worst is 18 days from the deadline.

Start with Restaurant chairs (80). SteelWorks is the supplier with the most value flagged.

Suppliers slipping after the order is placed is not in the data: ask each for a firm ship date.

$54K
5/9
Items flagged
5
9
Value at risk
$54K
Largest gap (days)
18
Share flagged
56%

Why rows were flagged

5
  • Arrives after deadline33%
  • Not yet ordered33%
  • Arrives within 7 days of deadline33%

Value flagged by Supplier

  • SteelWorks$21K
  • Milano Seating$18K
  • Nordic Joinery$8,200
  • SunDeck$6,800

Items to chase, largest first

ItemSupplierValueDaysWhy
Restaurant chairs (80)Milano Seating$12.4K14Arrives after deadline, Not yet ordered
Reception deskNordic Joinery$8,2004Arrives after deadline
Kitchen passSteelWorks$21K4Arrives within 7 days of deadline
Pool loungersSunDeck$6,8007Arrives within 7 days of deadline
Bar stools (24)Milano Seating$5,60018Not yet ordered

What to do this week

  • Call the supplier on Restaurant chairs (80) today and get a firm delivery date.
  • Ask SteelWorks for expedited shipping on its flagged items, or find alternatives.
  • Order every unordered item now: the lead time already uses up the time left.

Do

  • Compare arrival date, not order date, with the install deadline.

Don't

  • Don't accept a promised lead time without a ship date in writing.

How to improve

  • Add the supplier's confirmed ship date so the next report can use it instead of the promise.
  • Add whether the install can be re-sequenced so the next report can show the cost of waiting.

Demo

Try it now — free

Type your figures (or fill in samples) and get the answer in a minute.

Start from a template

Make it decision-ready

Also include

No card · no API key · your figures are not stored

Overview

An interiors project is judged on the day it opens, and that date is decided by one item: the longest lead time ordered latest. Everything else can be perfect and a space cannot be handed over with a missing headboard in every room.

The schedule is normally kept as a specification list — item, supplier, price, quantity, room — organised for procurement and for the client presentation, containing no dates. Lead time lives in whoever remembers it, and the item that fails is rarely the expensive one. It is the unremarkable one nobody worried about, made to order, from a supplier with a factory shutdown in August.

The compounding version is worse. Items are approved in batches at client meetings, so an approval slipping two weeks moves every order behind it, and the effect on the opening date is invisible until someone counts backwards from installation.

Counting backwards is the whole product: from the installation date, through delivery, shipping, production and the approval each item still needs, to the date the decision must actually be made.

This agent produces that path and names what is already late. It orders nothing and specifies nothing — substituting an item is a design decision.

Benefits

The opening date protected

Decided by one item, and now you know which.

Approvals prioritised by consequence

Rather than by whatever is easiest to decide.

Slippage seen while it is recoverable

Instead of at the installation programme.

What it does

  • Counts backwards from installation

    Through delivery, shipping, production and approval, to the date the decision must be made. The schedule holds none of this.

  • Finds the item that decides the date

    Rarely the expensive one. Usually something unremarkable, made to order, that nobody worried about.

  • Models approval batching

    Approvals happen at client meetings, so one slipping two weeks moves everything behind it.

  • Accounts for supplier shutdowns

    A factory closed for three weeks in August is not in any lead time figure and moves the date anyway.

  • Names what is already late

    Items whose decision date has passed, which is the only list that changes what happens this week.

  • Orders nothing

    It places no order and substitutes no item. A substitution is a design decision about the finished space.

What this changes

What this changes about your week

It takes over
Turning a furniture schedule into a dated critical path.
Done today by
Held in whoever remembers the lead times.
How often
Rarely, and usually after something is already late.
Typical manual effort
Counting backwards through delivery, shipping, production and approval for every item.

Why Interior Design in particular. The opening date is decided by one item — the longest lead time ordered latest — and it is rarely the expensive one. It is the unremarkable made-to-order item nobody worried about.

  • Runs unattended

    Started by you or by an event, and it finishes on its own. Nothing waits for someone to be at a desk.

  • The same standard every time

    The two-hundredth item is held to the bar the first one was. Consistency is the part people cannot sustain.

  • It cannot act on its own

    Furniture Schedule Lead Time Analyst has no path to sending, spending or committing. That limit is why its output is safe to act on.

How it runs

This agent runs server-side through the PROMIVO runtime. Each run is logged step by step and every tool call is permission-checked before it executes.

  1. 1InputValidated against the agent input schema
  2. 2Modelclaude-sonnet-5 with automatic fallback
  3. 3Toolsextract_structured_data
  4. 4PermissionsRuns READ actions automatically; anything higher waits for approval
  5. 5OutputStructured result matching the output schema
  6. 6LoggingTokens, duration and every step recorded

Requirements

Integrations

No integrations required.

Before you start

  • The furniture and fittings schedule: item, supplier, quantity, room
  • Lead times per item, and supplier shutdown periods
  • Installation and opening dates
  • Approval status per item, and client meeting dates
  • Requires the All-Access plan or higher

Use cases

After the schedule is signed off

The first time it becomes a dated plan.

Before each client approval meeting

Which decisions actually move the date.

When a date moves

What that does to everything behind it.

Multi-site rollouts

Where one supplier's capacity serves several openings.

Pricing

All-Access

Billed monthly through your PROMIVO subscription. Cancel at any time.

Runs consume your plan allowance for agent executions and tokens. See plan limits

FAQ

Does it place orders?

No. It places no order and contacts no supplier. It produces the dates and the consequences.

Will it suggest alternative products?

No. Substituting an item is a design decision about the finished space, and a schedule that quietly drifts toward whatever is available is how an interior stops being the one that was designed.

What if we do not have lead times for everything?

It reports those items as unknown rather than assuming a figure. An assumed lead time that is wrong is worse than an admitted gap, because it produces a plan people trust.

Reviews

Reviews open once customers have run this agent.

Need this agent to work differently?

Tell us what to change and our team will scope a customised version for your business.

Customize this agent